A project manager is having problems closing a project because the stakeholders did not accept the majority of the deliverables described in the project charter. What should the project manager do?
項(xiàng)目經(jīng)理在收尾一個(gè)項(xiàng)目時(shí)遇到問(wèn)題,因?yàn)橄嚓P(guān)方不接受項(xiàng)目章程中描述的大部分可交付成果,項(xiàng)目經(jīng)理應(yīng)該做?
A.Update the project charter更新項(xiàng)目章程
B.Submit a change request提交變更請(qǐng)求
C.Update the scope management plan更新范圍管理計(jì)劃
D.Validate the scope核實(shí)范圍
信管網(wǎng)參考答案:D
信管網(wǎng)解析:
D是參考答案。題干提出客戶對(duì)于章程中的項(xiàng)目成果不認(rèn)可。項(xiàng)目章程描述的是高層級(jí)范圍和可交付成果。項(xiàng)目成果正式驗(yàn)收工作是從過(guò)程5.5確認(rèn)范圍(Validate Scope)開(kāi)始的,在該過(guò)程中確認(rèn)每一個(gè)具體的可交付成果,從而提高最終產(chǎn)品獲得驗(yàn)收的可能性。同時(shí)過(guò)程5.5 使驗(yàn)收過(guò)程具有客觀性。選項(xiàng)D為過(guò)程5.5,參考PMBOK5.5關(guān)于過(guò)程定義的描述。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
由于超出項(xiàng)目經(jīng)理控制的原因,項(xiàng)目落后于進(jìn)度,一名有
在項(xiàng)目執(zhí)行期間,由于行業(yè)趨勢(shì)下行和產(chǎn)品價(jià)格下降,客
在測(cè)試期間,一位團(tuán)隊(duì)成員將某個(gè)質(zhì)量缺陷升級(jí)上報(bào)給項(xiàng)
在新項(xiàng)目啟動(dòng)會(huì)議期間,因?yàn)轫?xiàng)目將需要采購(gòu)新設(shè)備,生
技術(shù)進(jìn)步創(chuàng)造了一項(xiàng)組織需求,需要改善一個(gè)產(chǎn)品線的規(guī)
發(fā)表評(píng)論 查看完整評(píng)論 | |