A project manager working on a straightforward project receives repeated complaints from the site manager about the quality of the design team’s construction drawings. The project manager wants to identify possible actions to ensure that this problem will not recur. What should the project manager do first?
從事一個(gè)直接項(xiàng)目的項(xiàng)目經(jīng)理收到現(xiàn)場(chǎng)經(jīng)理關(guān)于設(shè)計(jì)團(tuán)隊(duì)施工圖紙質(zhì)量的反復(fù)投訴,項(xiàng)目經(jīng)理希望確定可能的行動(dòng),以確保不再發(fā)生這個(gè)問(wèn)題,項(xiàng)目經(jīng)理首先應(yīng)該怎么做?
A.Review the quality reports審查質(zhì)量報(bào)告B.B.Conduct a quality audit 開(kāi)展質(zhì)量審計(jì)
C.Perform a root cause analysis執(zhí)行根本原因分析
D.Create and analyze a causal-and-effect diagram創(chuàng)建并分析因果圖
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
C是參考答案。根本原因分析是管理質(zhì)量的工具,用于識(shí)別問(wèn)題的根本原因并解決問(wèn)題。消除所有根本原因可以杜絕問(wèn)題再次發(fā)生。參考章節(jié)8.2.2.2。B質(zhì)量審計(jì)主要用于識(shí)別問(wèn)題或良好的實(shí)踐。D因果圖有助于識(shí)別根本原因,但是題干同時(shí)強(qiáng)調(diào)確保不再發(fā)生這個(gè)問(wèn)題。C選項(xiàng)更加契合題干。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門(mén)公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專(zhuān)業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專(zhuān)業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿(mǎn)足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
項(xiàng)目發(fā)起人要求項(xiàng)目經(jīng)理立即開(kāi)始一個(gè)新項(xiàng)目,項(xiàng)目經(jīng)理
相關(guān)方已就項(xiàng)目可交付成果,關(guān)鍵里程碑以及角色與職責(zé)
一次項(xiàng)目會(huì)議后,市場(chǎng)營(yíng)銷(xiāo)經(jīng)理要求在公司網(wǎng)站上添加一
項(xiàng)目經(jīng)理希望確保相關(guān)方能充分參與項(xiàng)目的整個(gè)生命周期
一家推出一項(xiàng)新產(chǎn)品的公司估計(jì),實(shí)施質(zhì)量控制系統(tǒng)將花
發(fā)表評(píng)論 查看完整評(píng)論 | |