A change request was approved according to established change management procedures, during its implementation. a senior executive expresses surprise at not being involved in this approval, since the size and cost of the change was significant. What should the project manager have done to prevent this?
按照既定的變更管理程序,一項(xiàng)變更請求獲得批準(zhǔn),在實(shí)施該變更過程中,一位高級管理人員對其未參與批準(zhǔn)變更表示很驚訝,因?yàn)樵撟兏囊?guī)模和成本都很大。若要避免這個(gè)問題,項(xiàng)目經(jīng)理應(yīng)該事先做什么?
A.Established a change management process, the required different approval levels depending upon cost estimates制定變更管理流程,要求根據(jù)成本估算需要不同的審批級別
B.Ensured that the project team was trained to identify situations in which the senior executive should be involved in the change management process確保項(xiàng)目團(tuán)隊(duì)接受培訓(xùn),以識別該高級管理人員應(yīng)該參與變更管理流程的情況
C.Involve the senior executive in the design of the change management process during the project’s planning phase在項(xiàng)目的規(guī)劃階段,讓該高級管理人員參與變更管理流程的設(shè)計(jì)
D.Consulted with the senior executive prior to submitting the change request在提交變更請求之前先咨詢該高級管理人員的意見
信管網(wǎng)參考答案:C
信管網(wǎng)解析:
C是參考答案??键c(diǎn)在于制定項(xiàng)目管理計(jì)劃中變更管理計(jì)劃的編制,應(yīng)事先考慮關(guān)鍵干系人在變更處理過程中的角色、職責(zé)等內(nèi)容。A可以理解為是C的一項(xiàng)工作。
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |