During the second stage of a five-stage project, issues are encountered that must be resolved immediately, what should the project manager do?
在一個(gè)五階段項(xiàng)目的第二階段,遇到必須立即解決的問題,項(xiàng)目經(jīng)理應(yīng)該怎么做?
A.Meet with company executives and request more time to apply change control procedures與公司高管開會(huì),請(qǐng)求提供更多時(shí)間來應(yīng)用變更控制程序
B.Identify corrective actions, understand the schedule and cost impact, and employ the perform integrated change control process確定糾正措施,了解進(jìn)度和成本影響,并應(yīng)用實(shí)施整體變更控制過程
C.Quickly mobilize experts, fix the issues within the allotted time, and update the issue log, change log, schedule, budget and status report快速調(diào)動(dòng)專家,在規(guī)定的時(shí)間內(nèi)解決問題,并更新問題日志、變更日志、進(jìn)度計(jì)劃、預(yù)算和狀態(tài)報(bào)告
D.Roll back stage two’s delivery, update the schedule, and inform the project stakeholders回退第二階段的交付,更新進(jìn)度計(jì)劃,并通知相關(guān)方
信管網(wǎng)參考答案:B
信管網(wǎng)解析:
B是參考答案。針對(duì)問題,確定糾正措施,將糾正措施作為變更請(qǐng)求實(shí)施整體變更控制過程。其他選項(xiàng)均為可能的糾正措施,B為最合適答案。
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
從事一個(gè)直接項(xiàng)目的項(xiàng)目經(jīng)理收到現(xiàn)場(chǎng)經(jīng)理關(guān)于設(shè)計(jì)團(tuán)隊(duì)
項(xiàng)目發(fā)起人要求項(xiàng)目經(jīng)理立即開始一個(gè)新項(xiàng)目,項(xiàng)目經(jīng)理
相關(guān)方已就項(xiàng)目可交付成果,關(guān)鍵里程碑以及角色與職責(zé)
一次項(xiàng)目會(huì)議后,市場(chǎng)營(yíng)銷經(jīng)理要求在公司網(wǎng)站上添加一
項(xiàng)目經(jīng)理希望確保相關(guān)方能充分參與項(xiàng)目的整個(gè)生命周期
發(fā)表評(píng)論 查看完整評(píng)論 | |