While generating the status report for a budget-constrained project,the project manager identifies that the project is one week behind schedule. What should the project manager do t o bring the project back on track?查看答案
試題參考答案:A
試題2
項目發(fā)起人授權(quán)項目經(jīng)理編寫項目章程。項目經(jīng)理在收集高層次需求時,發(fā)現(xiàn)兩位高管意見有分歧,雖然項目經(jīng)理試圖引導他們達成一致,但效果甚微。項目經(jīng)理下—步應該怎么做?()查看答案
試題參考答案:B
試題3
Spike之后找出一個低風險的方案,作為敏捷工程師,你會怎么做?查看答案
試題參考答案:C
試題4
While reviewing the schedule,the project manager discovers is significant scope creep due to an unforeseen issue. What should the project manager do?查看答案
試題參考答案:C
試題5
項目經(jīng)理參與一個指導委員會召開的擴大會議。會議上,一位高級管理人員提出,項目團隊要能保證每位成員在要求的時間完成指定的工作。這屬于以下哪項管理范疇?查看答案
試題參考答案:C
試題6
Local experts warn that weather condition may impact the project schedule. What should the project manager do next?查看答案
試題參考答案:A
試題7
一個具體、定義明確的可交付成果正由一家公司位于某個成本較低國家的機構(gòu)開發(fā)。管理層決定將該部分公司出售給另一家組織。項目經(jīng)理被分配的任務是,替換該機構(gòu)提供的資源,完成可交付成果。查看答案
試題參考答案:B
試題8
A project manager is leading a team developing a new online banking application.After 23 months,the team has spent U SS100,000 on development and has US$70,000 of the budgeted cost remaining. The targeted completion date is 12 months away,but the team expects completion in nine months.A team member identifies a proven off-the-shelf product t hat complies with all project specifications,can be purchased for US$60,000,and can be implemented within eight months. What should the project manager consider?查看答案
試題參考答案:D
試題9
在定義范圍時,項目團隊識別到一個重大預算限制,并得到項目發(fā)起人的確認,若要提早識別到這個問題,項目經(jīng)理應該事先做什么?查看答案
試題參考答案:D
試題10
A project manager working on an IT development project dis covers that some codes supplied by a subcontractor fall to conform to project quality standards. The subcontractor refuses to change deliverables without additional payment guarantee s and extended timelines.A client debriefing is due in a few weeks. What should the project manager do?查看答案
試題參考答案:C
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |