信息系統(tǒng)項目管理師每日一練試題內(nèi)容(2025/3/17)
試題1
The (1) process differs from the (2) process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.
(1)A. Perform Quality Assurance
B. Validate Scope
C. Control Quality
D. Define Scope
(2)A. Perform Quality Assurance
B. Validate Scope
C. Control Quality
D. Define Scope
查看答案
試題參考答案:B、C
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題2
項目范圍基準(zhǔn)包括()查看答案
試題參考答案:A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題3
項目管理過程5個過程組可以對應(yīng)到PDCA循環(huán)中,()過程組與PDCA循環(huán)中的檢查和行動相對應(yīng)。查看答案
試題參考答案:C
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題4
在信息系統(tǒng)開發(fā)某個階段工作結(jié)束時,應(yīng)將工作產(chǎn)品及有關(guān)信息存入配置庫的( )。
A.受控庫
B.開發(fā)庫
C.產(chǎn)品庫
D.知識庫
查看答案
試題參考答案:A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題5
團隊成員的離職率降低,是()過程的輸出。
A、規(guī)劃資源管理
B、管理團隊
C、建設(shè)團隊
D、控制資源
查看答案
試題參考答案:C
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題6
Estimating schedule activity costs involves developing an(1 )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of (2 )to facilitate comparisons both within and across projects. The(3 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
(1)A. accuracy B. approximation C. specification D. summary
(2)A. activity B. work C. currency D. time
(3)A. project scope statement
B. statement of work
C. project management plan
D. project policy
查看答案
試題參考答案:B、C、A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題7
某公司的組織結(jié)構(gòu)如下圖所示,該公司采取的是( )組織結(jié)構(gòu)。查看答案
試題參考答案:A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題8
項目溝通管理是確保及時、正確地產(chǎn)生、收集、分發(fā)、()和處理項目信息所需的過程。查看答案
試題參考答案:A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題9
關(guān)于識別干系人過程的描述,不正確的是()查看答案
試題參考答案:C
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
試題10
在國家標(biāo)準(zhǔn)GB/T 8567-2006《計算機軟件文檔編制規(guī)范》中,將系統(tǒng)需求分成三大類,分別是()。查看答案
試題參考答案:A
試題解析與討論:m.xiexiliangjiufa.com/exam/ExamDay.aspx?t1=1&day=2025/3/17
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |