PMP®高頻錯(cuò)題(14)
高頻錯(cuò)題(14)
1、 [單選] 在項(xiàng)目執(zhí)行期間,一名團(tuán)隊(duì)成員經(jīng)常抱怨說(shuō)沒(méi)有及時(shí)提供某些信息。項(xiàng)目經(jīng)理應(yīng)該怎么做?
During project execution, a team member regularly complains that some information is not provided on a timely basis. What should the project manager do?
A:檢查該團(tuán)隊(duì)成員績(jī)效歷史記錄
Check the team member’s performance history.
B:與所有團(tuán)隊(duì)成員定期召開(kāi)情況通報(bào)會(huì)
Initiate regular information meetings with all team members.
C:與該團(tuán)隊(duì)成員召開(kāi)一對(duì)一的會(huì)議
Hold a one-on-one meeting with the team member
D:審查溝通管理計(jì)劃
Review the communications management plan.
正確答案:D 你的答案:C
解析:參考答案:D。 解析:PMBOK(6)P387,信息沒(méi)有及時(shí)的提供,是溝通出了問(wèn)題,應(yīng)該審查溝通管理計(jì)劃。
2、 [單選] 一位項(xiàng)目經(jīng)理正在與一個(gè)多元化的團(tuán)隊(duì)合作一個(gè)備受矚目公共工程項(xiàng)目。項(xiàng)目相關(guān)方的公共部門非常擔(dān)心,因?yàn)檫@個(gè)項(xiàng)目直接影響到他們的社區(qū)。項(xiàng)目經(jīng)理應(yīng)使用什么來(lái)與這個(gè)項(xiàng)目相關(guān)方團(tuán)體溝通?
A project manager is working on a high-profile public works project with a diverse and engaged group of stakeholders.The public sector of stakeholders is very concerned,as this project directly impacts their community.,What should the project manager use to communicate with this stakeholder group?
A:推式溝通
Push communication
B:交互式溝通
Interactive communication
C:項(xiàng)目相關(guān)方溝通
Stakeholder notifications
D:項(xiàng)目報(bào)告
Project reports
正確答案:B 你的答案:A
解析:需要達(dá)成一致意見(jiàn)的溝通,應(yīng)該使用交互式。
3、 [單選] 在批準(zhǔn)一位團(tuán)隊(duì)成員的緊急請(qǐng)假請(qǐng)求之前,項(xiàng)目經(jīng)理需要確保計(jì)劃的項(xiàng)目活動(dòng)不會(huì)被延遲。項(xiàng)目經(jīng)理首先應(yīng)該審查哪份文件?
Before approving a team member's request for an urgent leave, a project manager needs to ensure that scheduled activities will not be delaye What should the project manager first review?
A:責(zé)任分配矩陣(RAM)
Responsibility assignment matrix(RAM)
B:資源日歷
Resource calendars
C:資源分解結(jié)構(gòu)(RBS)
Resource breakdown structure(RBS)
D:項(xiàng)目進(jìn)度計(jì)劃
Project schedule plan
正確答案:D 你的答案:B
解析:參考答案:D。解析:PMBOK(6)P352。資源日歷影響項(xiàng)目日歷,現(xiàn)在資源日歷將發(fā)生改變,要對(duì)照項(xiàng)目日歷(項(xiàng)目計(jì)劃開(kāi)展活動(dòng)的時(shí)間,即項(xiàng)目進(jìn)度計(jì)劃)分析對(duì)進(jìn)度的影響。
4、 [單選] 項(xiàng)目經(jīng)理需要從不同職能經(jīng)理招募團(tuán)隊(duì)成員,項(xiàng)目經(jīng)理應(yīng)使用什么?
A project manager needs to acquire team members from various functional managers. What should the project manager use?
A:資源日歷
Resource calendars
B:協(xié)商
Negotiation
C:募集
Acquisition
D:技能圖
Skill mapping
正確答案:A 你的答案:B
解析:參考答案:A。解析:PMBOK(6)P322,從其他項(xiàng)目獲取資源應(yīng)估算活動(dòng)資源的可用時(shí)間,用到的工具是資源日歷。故選A。此題A和B容易混淆,A在B前面,按照選前不選后原則,這題選A,先根據(jù)資源日歷選擇好需要的資源,然后和職能經(jīng)理協(xié)商。
5、 [單選] 項(xiàng)目經(jīng)理發(fā)現(xiàn)沒(méi)有關(guān)于需要哪些部門資源的信息,應(yīng)該在哪一份文件中更新該信息?
A project manager discovers that there is no information on what department resources are requirewhat document should be updated with this information?
A:項(xiàng)目章程
Project charter
B:組織結(jié)構(gòu)圖
Organizational chart
C:項(xiàng)目管理計(jì)劃
Project management plan
D:風(fēng)險(xiǎn)管理計(jì)劃
Risk management plan
正確答案:C 你的答案:B
解析:9.1 規(guī)劃資源管理 資源信息應(yīng)該包含在資源管理計(jì)劃中,屬于項(xiàng)目管理計(jì)劃一部分。此題容易錯(cuò)選B,組織結(jié)構(gòu)圖也是一種資源信息。
6、 [單選] 一個(gè)虛擬團(tuán)隊(duì)正在為一個(gè)全球客戶開(kāi)發(fā)一個(gè)項(xiàng)目。由于組織重組,團(tuán)隊(duì)將從70人減少到58人,項(xiàng)目經(jīng)理應(yīng)該怎么做?
A virtual team is working on a project for a customer with global presence. Due to organizational restructuring, the team will be reduced from 70 to 58 members. What should the project manager do?
A:將剩余的團(tuán)隊(duì)成員集中在一起辦公,以提高他們作為團(tuán)隊(duì)執(zhí)行工作的能力
Co-location the remaining team members to enhance their ability to perform as A team
B:獲得額外資金以改善溝通技術(shù),以便在團(tuán)隊(duì)成員之間建立更好的共識(shí)
Obtain additional funds to improve communication technology to build better understanding among team members
C:通過(guò)使用新的可用信息更新項(xiàng)目管理計(jì)劃來(lái)采取預(yù)防措施
Take preventive actions by updating the project management plan with the newly available information
D:更新工作分解結(jié)構(gòu)(WBS)并確保所有活動(dòng)按時(shí)完成
Update the work breakdown structure (WBS) and ensure that all activities are completed on time
正確答案:B 你的答案:A
解析:虛擬團(tuán)隊(duì),關(guān)注溝通。題干已說(shuō)明是虛擬團(tuán)隊(duì),這是限制條件,因此不能集中辦公,A不對(duì);C和D都要走變更流程,因此不選;B獲取資金已包含走流程的含義。
————————————————
版權(quán)聲明:本文為CSDN博主「LK_Tracking」的原創(chuàng)文章,遵循CC 4.0 BY-SA版權(quán)協(xié)議,轉(zhuǎn)載請(qǐng)附上原文出處鏈接及本聲明。
原文鏈接:https://blog.csdn.net/weixin_40039983/article/details/108405385
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
相關(guān)內(nèi)容