信息系統(tǒng)項(xiàng)目管理師每日一練試題內(nèi)容(2022/8/13)
試題1
The( )technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
A. Cost Aggregation
B. Reserve Analysis
C. Parametric Estimating
D. Funding Limit Reconciliation
查看答案
試題參考答案:C
試題2
() includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . Managing the project scope is primarily concerned with defining and controlling what is not included in the project.查看答案
試題參考答案:C
試題3
知識管理的工具通常分為()三大類。
A、知識生成工具、知識分析工具、知識傳播工具
B、知識采集工具、知識合成工具、知識轉(zhuǎn)移工具
C、知識生成工具、知識編碼工具、知識轉(zhuǎn)移工具
D、知識采集工具、知識分類工具、知識傳播工具
查看答案
試題參考答案:C
試題4
在信息系統(tǒng)生命周期中,首先要進(jìn)行信息系統(tǒng)規(guī)劃,之后開展系統(tǒng)分析工作。()不屬于系統(tǒng)規(guī)劃階段的工作。查看答案
試題參考答案:A
試題5
某公司網(wǎng)管員對核心數(shù)據(jù)的訪問進(jìn)行控制時(shí),針對每個(gè)用戶指明能夠訪問的資源,對于不在指定資源列表中的對象不允許訪問。該訪問控制策略屬于( )。
A.自主訪問控制(DAC)
B.強(qiáng)制訪問控制(MAC)
C.基于角色的訪問控制(RBAC)
D.訪問控制列表方式(ACL)
查看答案
試題參考答案:A
試題6
項(xiàng)目可行性研究階段的經(jīng)營成本不包括()。查看答案
試題參考答案:A
試題7
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail
查看答案
試題參考答案:C
試題8
Project Risk Management processes consist of the following elements , except :()。查看答案
試題參考答案:A
試題9
網(wǎng)絡(luò)路由器( )
A、可以連接不同的子網(wǎng)
B、主要用于局域網(wǎng)接入internet
C、主要起分隔網(wǎng)段的作用
D、工作于數(shù)據(jù)鏈路層
查看答案
試題參考答案:A
試題10
( )不是項(xiàng)目目標(biāo)特性。
A.多目標(biāo)性
B.優(yōu)先性
C.臨時(shí)性
D.層次性
查看答案
試題參考答案:C
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |