2009年上半年信息系統(tǒng)項目管理師考試英語真題
Many of the activities performed during the preliminary investigation are still being conducted in( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the( ) and must develop enough knowledge about the( ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the( ) for process and data of current system, the deliverable from this phase also includes the( ) for the proposed system.
( )A. analysis phase B. design phase
C. implementation phase D. maintenance phase
( )A. main symptom B. root problem
C. final blueprint D. data specification
( )A. hardware environment B. testing environment
C. software environment D. business environment
( )A. logical models B. physical models
C. design models D. implementation models
( )A. hardware and software specification B. system performance specification
C. formal requirements definition D. general problem statement
信管網(wǎng)解析:
初步調(diào)研階段的許多活動在分析階段仍然要做,但是會比以前更深入地做。在分析階段,分析師一定要完全清楚最終藍圖并且開發(fā)出充分的關(guān)于業(yè)務(wù)環(huán)境知識和目前系統(tǒng)的知識以使一個有效的解決方案被提交和實施。除了當(dāng)前系統(tǒng)的過程和數(shù)據(jù)的邏輯模型,這一階段的產(chǎn)出物還包括建議系統(tǒng)的正式需求定義。
信管網(wǎng)參考答案: A, B, D, A, C
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!