71、The main steps of IT strategic planning don't inclade()。
A.Business Analysis
B.Evaluate the competetor's system
C.Identify Opportanities
D.Selection Seheme
【參考答案】B
【答案以信管網(wǎng)題庫(kù)為準(zhǔn)-查看解析】m.xiexiliangjiufa.com/st/521646562.html
72、The best description of an operational level Agreement(OLA)is()。
A. an agreement between the serivice provider and another part of the same Drganization
B.an agreement between the serivice provider and an exterral organization
C.a docament that describes how services will be operated on a day -to -day basis to customer
D.a docament that business services to operational staff
【參考答案】C
【答案以信管網(wǎng)題庫(kù)為準(zhǔn)-查看解析】m.xiexiliangjiufa.com/st/521655414.html
73、The processess of knowledge content Initialization don't include()。
A.obtain
B.audit
C.release
D.edit
【參考答案】D
【答案以信管網(wǎng)題庫(kù)為準(zhǔn)-查看解析】m.xiexiliangjiufa.com/st/521666141.html
74題暫缺
75、The type of measurement index does not include which()。
A、process indication
B、data indication
C、Resources indication
D、process indication
【參考答案】B
【答案以信管網(wǎng)題庫(kù)為準(zhǔn)-查看解析】m.xiexiliangjiufa.com/st/5216827855.html
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |